It is a modification of the existing technological bridge, including the complete technology. The subject of performance was also the delivery and putting into operation of the technological set of the loading node, which allows loading FGD gypsum into railway wagons.
The realization of the contract started in April this year and the production of the new technology is currently in progress. In the next phase of the project, the installation of the new technology will be launched during July. The expected completion and commissioning is scheduled for autumn 2019.